NEW QUESTION 1
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

  • A. Cost baseline
  • B. Cost forecasting
  • C. Cost variance
  • D. Cost budgeting

Answer: D

NEW QUESTION 2
Which of the following tools and techniques are utilized in the Close Project or Phase process?

  • A. Project management information system
  • B. Product analysis
  • C. Expert judgment
  • D. Inspection

Answer: C

NEW QUESTION 3
Resource calendars are included in the:

  • A. staffing management plan.
  • B. work breakdown structure (WBS).
  • C. project communications plan.
  • D. project charter.

Answer: A

NEW QUESTION 4
Which process should be conducted from the project inception through completion?

  • A. Monitor and Control Project Work
  • B. Perform Quality Control
  • C. Perform Integrated Change Control
  • D. Monitor and Control Risks

Answer: C

NEW QUESTION 5
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

  • A. Program Management Body of Knowledge Guide
  • B. The Standard for Program Management
  • C. Organizational Project Management Maturity Model (OPM3$)
  • D. Guide to the Project Management Body of Knowledge (PMBOK®)

Answer: D

NEW QUESTION 6
The purpose of inspection in Perform Quality Control is to keep errors:

  • A. in line with a measured degree of conformity.
  • B. out of the hands of the customer.
  • C. in a specified range of acceptable results.
  • D. out of the process.

Answer: C

NEW QUESTION 7
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

  • A. project documents updates.
  • B. project management plan updates.
  • C. change requests.
  • D. work performance information.

Answer: D

NEW QUESTION 8
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

  • A. Supportive
  • B. Directive
  • C. Controlling
  • D. Instructive

Answer: A

NEW QUESTION 9
What is the difference between the critical path and the critical chain?

  • A. Scope changes
  • B. Resource limitations
  • C. Risk analysis
  • D. Quality audits

Answer: B

NEW QUESTION 10
Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?

  • A. Analogous Estimating
  • B. Expert Judgment
  • C. Optimistic Estimates
  • D. Reserve Analysis

Answer: D

NEW QUESTION 11
Issue change requests and adapt approved changes into the project’s scope, plans, and environment is an activity included in which of the following project management processes?

  • A. Direct and Manage Project Execution
  • B. Monitor and Control Project Work
  • C. Perform Integrated Change Control
  • D. Monitor and Control Risks

Answer: A

NEW QUESTION 12
Work performance information and cost forecasts are outputs of which Project Cost Management process?

  • A. Estimate Costs
  • B. Plan Cost Management
  • C. Determine Budget
  • D. Control Costs

Answer: D

NEW QUESTION 13
During which process group is the quality policy determined?

  • A. Initiating
  • B. Executing
  • C. Planning
  • D. Controlling

Answer: C

NEW QUESTION 14
Which of the following is a tool or technique for the Plan Procurements process?

  • A. Bidder conferences
  • B. Proposal evaluation techniques
  • C. Contract types
  • D. Contract change control systems

Answer: C

NEW QUESTION 15
Within project integration management, the statement of work (SOW) references which aspects of the project?

  • A. Strategic plan, business need, and product scope description
  • B. Contract, enterprise environmental factors, and organizational process assets
  • C. Business plan, project management plan, and project schedule
  • D. Product lifecycle, business objective, and management strategy

Answer: A

NEW QUESTION 16
Which of the following is an example of contract administration?

  • A. Negotiating the contract
  • B. Authorizing contractor work
  • C. Developing the statement of work
  • D. Establishing evaluation criteria

Answer: B

NEW QUESTION 17
The links between the processes in the Process Groups are often:

  • A. Intuitive
  • B. Iterative
  • C. Measured
  • D. Monitored

Answer: B

NEW QUESTION 18
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

  • A. 0.03
  • B. 0.06
  • C. 0.10
  • D. 0.50

Answer: B

NEW QUESTION 19
The process of developing a detailed description of the project and product is known as:

  • A. Create WBS.
  • B. Verify Scope.
  • C. Collect Requirements.
  • D. Define Scope.

Answer: D

NEW QUESTION 20
The following chart contains information about the tasks in a project.
PMP dumps exhibit
Based on the chart, what is the cost performance index (CPI) for Task 2?

  • A. 0.8
  • B. 1
  • C. 1.25
  • D. 1.8

Answer: C