Testking offers free demo for PK0-003 exam. "CompTIA Project+ (2009)", also known as PK0-003 exam, is a CompTIA Certification. This set of posts, Passing the CompTIA PK0-003 exam, will help you answer those questions. The PK0-003 Questions & Answers covers all the knowledge points of the real exam. 100% real CompTIA PK0-003 exams and revised by experts!

Q31. - (Topic 2) 

Which of the following items would be found in a project scope statement? 

A. Key performance indicators 

B. High-level cost estimates 

C. Acceptance criteria 

D. Bottom-up estimates 

Answer:


Q32. - (Topic 3) 

All of the following are characteristics of a project EXCEPT that it: 

A. is managed by consensus. 

B. is a temporary endeavor to create a unique product or service. 

C. is limited by human and financial resources. 

D. adheres to the triple constraint. 

Answer:


Q33. - (Topic 3) 

Which of the following are tools used in quality control? (Select TWO). 

A. Gantt chart 

B. Ishikawa diagram 

C. Parametric estimating 

D. Probability and impact matrix 

E. Pareto chart 

Answer: B,E 


Q34. - (Topic 2) 

A project activity has a schedule that allows a late start on day 10 and a late finish on day 

20. The project manager has determined an early start could occur on day 7 with an early finish on day 14. Which of the following does this schedule identify? 

A. A lead 

B. A buffer 

C. A float 

D. A lag 

Answer:


Q35. - (Topic 1) 

Which of the following steps is required to validate a business case? 

A. Feasibility analysis 

B. Assign costs 

C. Schedule milestones 

D. Identify project scope 

Answer:


Q36. - (Topic 2) 

A project manager has uncovered that the optimal weight of the magnet that the stakeholders approved for the project is wrong. Which of the following BEST illustrates the problem? 

A. Pareto chart 

B. Ishikawa diagram 

C. PERT diagram 

D. Gantt chart 

Answer:


Q37. - (Topic 3) 

When creating a network diagram, the project manager identifies a relationship between tasks A, B, and C, wherein A must start before B, but B and C may be started at the same time. In this scenario, A is BEST defined as a: 

A. start to start dependency type. 

B. successor to C. 

C. predecessor to B. 

D. finish to start dependency type. 

Answer:


Q38. - (Topic 2) 

A WBS dictionary can be used to define which of the following? 

A. Deliverables 

B. Constraints 

C. Assumptions 

D. Activities 

Answer:


Q39. - (Topic 1) 

A coworker approaches the project manager regarding a project team member’s prior work ethic. Which of the following is the BEST approach for the project manager to address the information presented? 

A. Do not act on the information presented 

B. Ask the resource manager for another resource 

C. Discuss the issue with human resources 

D. Confront the resource manager about the risk 

Answer:


Q40. - (Topic 2) 

A project involves outsourcing multiple parts of the software application to developers around the world. Which of the following is MOST likely to impact meeting attendance? 

A. Time zone differences 

B. Cultural differences 

C. Language barriers 

D. Technology barriers 

Answer: