Q41. - (Topic 3) 

A project manager is holding a workshop to identify objectives, review legal and regulatory requirements, and establish and maintain performance measures. Which of the following is being performed? 

A. Quality control 

B. Quality objectives 

C. Quality assurance 

D. Quality audit 

Answer:


Q42. - (Topic 3) 

A project manager is considering crashing the project schedule to bring the project back on schedule. Which of the following should be considered? (Select TWO). 

A. The cost baseline will need to be updated 

B. The critical path may change 

C. The scope will decrease 

D. The project SPI will remain unchanged 

E. Costs will increase 

Answer: B,E 


Q43. - (Topic 3) 

Which of the following would MOST likely be found in the quality management plan? (Select TWO). 

A. Resource quality policies 

B. Quality assurance process description 

C. Risk register 

D. Frequency of quality measurement 

E. Manufacturing specification details 

F. Quality cost calculations 

Answer: B,D 


Q44. - (Topic 1) 

A project team has to implement a key part of their solution from an external vendor. After sending out an RFP, the team has narrowed the possible providers down to three. Which of the following should the project manager do NEXT? 

A. Hold a steering committee meeting to discuss the options 

B. Ask the project team to take a vote on the vendor 

C. Begin contract negotiations with the lowest offer 

D. Contact project stakeholders individually and discuss the RFP 

Answer:


Q45. - (Topic 1) 

Resources in another country have reported that they are losing two to three hours of productive work time due to server reboots that are happening daily. Which of the following should the project manager take into account when seeking a solution to the issue? 

A. Language barriers 

B. Time zones 

C. Project schedule 

D. Work styles 

Answer:


Q46. - (Topic 3) 

A project team is building an internal application that may be marketed to outside customers. Which of the following is considered the MOST appropriate risk response? 

A. Avoidance 

B. Mitigation 

C. Exploiting 

D. Acceptance 

Answer:


Q47. - (Topic 3) 

Which of the following include the WBS as an input? 

A. Project scope statement 

B. Project schedule 

C. Project charter 

D. Project requirements 

Answer:


Q48. - (Topic 1) 

The project team members have determined they need to procure hardware before they will be able to create a product to test. This activity sequencing was created using which of the following types of dependency? 

A. Mandatory 

B. External 

C. Discretionary 

D. Internal 

Answer:


Q49. - (Topic 2) 

Who is responsible for implementing scope modifications on a project? 

A. Project sponsor 

B. Senior manager 

C. Project manager 

D. Product owner 

Answer:


Q50. - (Topic 1) 

When a project manager is leading the team through the norming stage of team growth, the project team: 

A. is performing in a highly efficient manner. 

B. has reached full capacity. 

C. is seeing a decrease in productivity. 

D. is working together and comfortable. 

Answer: