Want to know Testking PK0-003 Exam practice test features? Want to lear more about CompTIA CompTIA Project+ (2009) certification experience? Study Exact CompTIA PK0-003 answers to Replace PK0-003 questions at Testking. Gat a success with an absolute guarantee to pass CompTIA PK0-003 (CompTIA Project+ (2009)) test on your first attempt.

2017 Apr PK0-003 free download

Q141. - (Topic 1) 

A project is a (an): 

A. specific solution. 

B. business strategic plan. 

C. group of products. 

D. ongoing endeavor. 

Answer:


Q142. - (Topic 2) 

Which of the following conflict management techniques is represented by making concessions to maintain team harmony? 

A. Smoothing 

B. Negotiating 

C. Collaborating 

D. Avoiding 

Answer:


Q143. - (Topic 2) 

A project manager has identified several risks for the project during the initial project implementation. As risks continue to be found and other risks get closed, which of the following is the main output? 

A. Initial risk assessment 

B. Risk matrix 

C. Risk register 

D. Stakeholder risk tolerance 

Answer:


Q144. - (Topic 2) 

A project manager is assembling a project team. Which of the following will be MOST effective in ensuring team members contribute appropriately to the team? 

A. Communicate stakeholder expectations 

B. Define roles and responsibilities 

C. Address team conflicts as they arise 

D. Schedule regular team building exercises 

Answer:


Q145. - (Topic 1) 

Which of the following areas is addressed in the Project Charter? 

A. Project team members 

B. Work Breakdown Structure (WBS) 

C. Business needs 

D. Communications venue 

Answer:


Improve PK0-003 test preparation:

Q146. - (Topic 2) 

When working on the monitoring and controlling phase of the project lifecycle, which of the following activities would occur? 

A. Third-party auditors will evaluate documentation. 

B. Team members will participate in lessons learned events. 

C. Project manager will direct and manage work tasks. 

D. Senior management will review the project scope document. 

Answer:


Q147. - (Topic 3) 

Once a change request has been approved by the Change Control Board, which of the following should the project manager do FIRST? 

A. Request additional funding 

B. Perform an impact analysis 

C. Update the project plan 

D. Inform the project team 

Answer: C


Q148. - (Topic 2) 

Which of the following is the status of an active project with an SPI of 1.1 and a CPI of .9? 

A. Behind schedule, and over budget 

B. Ahead of schedule, and under budget C. Behind schedule, and under budget 

D. Ahead of schedule, and over budget 

Answer:


Q149. - (Topic 2) 

Although a needed item can be made in-house, it has been determined that it will be procured. Since the scope is well-defined, which of the following procurement documents should be used and which contract type should result? 

A. Request for proposal, and cost plus contract 

B. Request for quote, and time and material contract 

C. Request for bid, and fixed price contract 

D. Request for information, and unit price contract 

Answer:


Q150. - (Topic 3) 

A project manager determines the following from a network diagram: 

Work item A – 3 day duration – first work item to start 

Work item B – 7 day duration – starts when A is complete 

Work item C – 2 day duration – can start when A starts 

Work item D – 1 day duration – can start when B is complete 

Which of the following comprise the critical path? 

A. A, B, D 

B. A, B, C 

C. A, C, D 

D. A, C, B 

Answer: